View Categories
Attendance Workflow When Using Payroll

bitKode — Attendance #

Attendance Workflow When Using Payroll #

1. Book and Approve All Leave First

Do this before you touch Attendance. All leave for the period needs to be in the system and approved.

  1. Make sure all leave has been booked.
  2. Check for any pending leave requests and approve them.
  3. Add any leave entries that are missing.

If you add leave after Attendance is already processed, the system will mark those days as Out of Date.

You will then have to reprocess Attendance again.

2. Process Attendance #

Once all leave is sorted, go to the Attendance module and click Process Attendance.

The system will then work out all the clock-in and clock-out pairs. It will show you:

  1. Valid clocking pairs – these are fine.
  2. Invalid clockings – these need to be fixed before you can move on.

For step-by-step help, see the Process Attendance Period guide.

3. Fix All Invalid Clockings #

Invalid clockings are days where the clock-in or clock-out is missing or wrong. You need to fix each one before you can approve anything.

  1. Open the Requires Your Attention section.
  2. Go through each invalid entry one by one and add any missing manual punches.
  3. Click Save and close each entry when done.
  4. Refresh the page and confirm the list is clear.

⚠ If you leave invalid clockings unfixed, the system will block approvals and you won’t be able to send hours to Payroll.

See the Handle Invalid Clockings guide for help.
4. Process Out-of-Date Clockings

Any time you add or change a punch, the system marks that record as Out of Date. This means it needs to be recalculated.

  1. Open the Out of Date section.
  2. Process each entry so the system can rebuild the correct clock-in/clock-out pair.
  3. Refresh the page and make sure the list is empty before moving on.

See the Handle Invalid Clockings guide for help.

5. Override the Schedule If needed #

This step only applies in certain situations. For example: an employee worked a night shift, but their schedule is set to flexible and doesn’t cover night hours. In that case, you need to apply a schedule override for that day.

See the Override a Schedule guide for how to do this.

6. Approve the Hours #

Before you approve anything, check that all of the following are done:

  1. All leave is booked and approved.
  2. Attendance has been processed.
  3. All invalid clockings are fixed.
  4. All Out-of-Date entries are cleared.

Once everything above is done, go to the Approve Hours section and approve:

  1. Overtime
  2. Short hours
  3. Attendance

You must complete this step before hours can go into the pay run.

7. Send the Approved Hours to the Pay Run #

You are now ready to transfer the hours into the pay run.

Follow the Lock Attendance Dates to Transfer to Payroll guide to complete this step.


Quick Reference – Step Order #

Always follow this order. Skipping or swapping steps will cause errors.

Step What to do
1 Book and Approve All Leave
2 Process Attendance
3 Fix All Invalid Clockings
4 Process All Out-of-Date Entries
5 Override the Schedule (If Needed)
6 Approve Hours
7 Send Approved Hours to the Pay Run

Why the Order Matters #

✓Hours are calculated correctly.
✓No hours go missing or get counted twice.
✓Approvals go through without getting stuck.
✓Hours transfer to Payroll without issues.
✓The pay run goes out on time.
⚠ If you skip a step or do them out of order, you may get errors, blocked approvals, or wrong payroll results.
This process must be followed every pay cycle.